REQUEST FOR QUOTES SANITARY SEWER REPAIR AT 1608 Broadway

Bidders ID: NBD24400587129678446
Due Date: Nov 19, 2026
Posted Date: Oct 29, 2026
Level of Government: State & Local
State: Indiana
Agency: Gary Sanitary District
Category:
  • J - Maintenance, Repair, and Rebuilding of Equipment
  • Z - Maintenance, Repair or Alteration of Real Property
Source: Members Only


Project ID:

Title: REQUEST FOR QUOTES SANITARY SEWER REPAIR AT 1608 Broadway

Addenda: 0

Release Date: 10/29/2026

Due Date: 11/19/2026

Follow
REQUEST FOR QUOTES SANITARY SEWER REPAIR AT 1608 Broadway
Request For Proposal
Engineering
67012 , 91063 , 91345 , 91381
Project ID: 2026-RFP-063
Release Date: Thursday, October 29, 2026
· Due Date: Thursday, November 19, 2026 2:00pm
Posted Thursday, October 29, 2026 2:21pm
All dates & times in Central Time - Chicago
Draft Response No Bid20 days, 18 hours, 16 minutes


Post Information

Posted At:Thu, Oct 29, 2026 2:21 PM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Overview


Summary

Sanitary Sewer Repair at 1608 Broadway in the City of Gary, IN.

Furnish all labor, materials, tools, equipment, superintendence, and all necessary incidentals for the repair of sanitary sewer pipe.

Manhole No. 507 Sewer Invert Depth is ± 13.7

Manhole No. 508 Sewer Invert Depth is ± 13.9

POINT REPAIR

Remove and replace existing 15-inch diameter pipe with 15-inch diameter PVC SDR 35 ± 30-linear feet from Manhole No. 508 going towards Manhole No. 507.

CIPP LINING

    • CIPP line existing 15-inch diameter pipe x 190 linear feet starting from Manhole No. 508 to Manhole No. 507.


Background

POINT REPAIR

  • Remove and replace existing 15-inch diameter pipe with 15-inch diameter PVC SDR 35 ± 30-linear feet from Manhole No. 508 going towards Manhole No. 507.
  • Contractor shall ensure pipe penetrations are sealed and watertight.
  • Contractor shall connect new pipe to existing good pipe with a watertight connection. Connect new pipe to existing PVC pipe with neoprene rubber coupling with stainless steel straps or coupling provided by the manufacturer and approved by the owner. When adjoining new pipe to existing, the maximum space between the abutting pipes shall be 1/8 inches or less.

CIPP LINING

  • CIPP line existing 15-inch diameter pipe x 190 linear feet starting from Manhole No. 508 to Manhole No. 507.
  • The CIPP liner shall extend 4-inches into existing manholes.
  • The Contractor shall install a pre-liner and/or perform chemical grouting of infiltration points as necessary


Timeline

Release RFP Date:
October 29, 2026
Question Submission Deadline:
November 12, 2026, 12:00pm
Proposal Submission Deadline:
November 19, 2026, 2:00pm
Disclaimer: The details regarding bids, requests for proposals (RFPs), and requests for qualifications (RFQs) on this site are provided for convenience and do not represent official public notice. To respond to or inquire about bids, RFPs, or RFQs, please contact the appropriate government department.

TRY FOR FREE

Not a GovernmentBidders Member Yet?

Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.

Start Free Trial Today >