Request for Proposals for Gross Reservoir Expansion Project Bank Stabilization Monitoring on South Boulder Creek and North Fork South Platte
| Bidders ID: | NBD23486327024106326 |
|---|---|
| Due Date: | Jul 8, 2026 |
| Posted Date: | Jun 5, 2026 |
| Level of Government: | State & Local |
| State: | Colorado |
| Agency: | Denver Water |
| Category: |
|
| Source: | Members Only |
Engineering
Contract or Solicitation Number:
Solicitation Description:
Denver Water is seeking a firm to monitor bank stabilization on South Boulder Creek and the North Fork South Platte River. Interested firms will submit a proposal to complete monitoring and reporting activities on both streams.
Post Date:
June 4, 2026
Due Date:
July 8, 2026
Solicitation Documents:
Attachment Preview
Gross Reservoir Expansion Project
Request for Proposal
Gross Reservoir Expansion (GRE) Project
Bank Stabilization Monitoring on South Boulder Creek and North Fork South Platte
Request for Proposals (RFP)
Submission Deadline: 2:00 pm (MT), Wednesday, July 8, 2026
Section 1 – Introduction, Background, & History
Introduction
Denver Water is seeking a firm to monitor bank stabilization on South Boulder Creek and the North Fork South
Platte River. The selection process involves interested firms submitting a proposal to complete monitoring and
reporting activities on both streams; followed by consultant interviews, selection, and contract award.
Background & History
Denver Water began the process of permitting the Gross Reservoir Expansion (GRE) Project in 2003. The U.S.
Army Corps of Engineers was the lead federal agency in regard to preparation of the Environmental Impacts
Statement (EIS) and issued a Clean Water Act Section 404 Permit in 2017. Prior to issuance of the 404 Permit,
Denver Water entered into two agreements requiring monitoring of stream bank stability below transmountain
diversions. The first was with Colorado Parks and Wildlife (CPW; 2011) and the second was with the U.S. Forest
Service (USFS; 2016) which was adopted into Denver Water’s 2020 Federal Energy Regulatory Commission
(FERC) License for Gross Reservoir hydropower operations.
Section 2 – Phase 1 Overview
Consultant Scope of Work Overview
Based on the requirements listed below, develop a scope of work (SOW) to meet the field monitoring
requirements and prepare one annual report for CPW and the USFS for each year field monitoring takes place.
Project Assumptions
The following assumptions were made in the development of this SOW:
• This project will be developed and coordinated in Denver Water’s SharePoint platform. Denver Water
will utilize the existing GRE Project SharePoint site and will establish a Microsoft Teams channel for
collaborative use by the internal and external project design team members.
• The Consultant’s SOW shall be focused on meeting the requirements of the streambank monitoring
program shown below. Contract amendments for additional scope will be considered by Denver
Water based on the Consultant’s performance and project progress.
o Phase 1 will be for monitoring and reporting of baseline conditions (Baseline Streambank
Monitoring and Reporting).
o Phase 2 will be for monitoring and reporting during initial fill of the expanded reservoir (Initial
Fill Monitoring and Reporting).
o Phase 3 will be for monitoring and reporting post initial fill of the expanded reservoir (Long-
term Monitoring and Reporting).
• The initial funding approval will cover Phase 1. Subsequent funding for Phase 2 and Phase 3 will be
approved utilizing contract amendments.
Page 1 of 12
Gross Reservoir Expansion Project
Request for Proposal
Project Objectives
The objectives of this effort are to:
• Monitor channel instability and bank erosion in accordance with FERC license conditions.
• Implement Control–Impact monitoring frameworks for both river systems.
• Provide defensible geomorphic and biological data to support adaptive management.
• Support interagency coordination with USFS and CPW.
• Prepare restoration plans and support implementation if stabilization or restoration is required.
Section 3 – Schedule
Consultant Selection Schedule
The anticipated schedule for proposals and award is summarized below:
• Final Written Questions Due ----------------------------------June 17, 2026
• Addendum Posted ---------------------------------------------June 22, 2026
• Proposals Due -------------------------------------------------July 8, 2026
• Interviews ------------------------------------------------------July 15, 2026
• Selection -------------------------------------------------------July 22, 2026
• Notice to Proceed ----------------------------------------------------- September 1, 2026
Page 2 of 12
Gross Reservoir Expansion Project
Request for Proposal
Overall Project Schedule
Denver Water has developed the following conceptual schedule for data collection and report submittal:
Phase 1 - Baseline Streambank Monitoring and Reporting
• Year 1 Baseline Data Collection ----------------------------------- September/October 2026
• Year 1 Report ---------------------------------------------------------- February 2027
• Year 2 Baseline Data Collection (if needed) --------------------- September/October 2027
• Year 2 Report ---------------------------------------------------------- February 2028
Phase 2 – Initial Fill and Reporting
• Year 3 Data Collection (initial fill year 1) -------------------------- September/October 2028
• Year 3 Report ---------------------------------------------------------- February 2029
• Year 4 Data Collection (initial fill year 2) -------------------------- September/October 2029
• Year 4 Report ---------------------------------------------------------- February 2030
• Year 5 Data Collection (initial fill year 3) ------------------------- September/October 2030
• Year 5 Report ----------------------------------------------------- ---- February 2031
Phase 3 – Long-term Monitoring and Reporting
• Once every 3 years for 9 years (3 sampling events).
• Once every 5 years for 15 years (3 sampling events).
• High flow years (>55,000 AF at east portal of Moffat or Roberts tunnels [May, June, July]).
Proposals shall include a detailed schedule for the three work Phases with any deviations from the
aforementioned schedule clearly identified (see Task 3.5). The initial funding approval will cover Phase 1.
Subsequent funding for Phase 2 and Phase 3 will be approved utilizing a new contract or contract
amendments.
Page 3 of 12
Gross Reservoir Expansion Project
Request for Proposal
Section 4 – Scope of Work
Denver Water has prepared the following SOW for Phase 1 of the Bank Stability on South Boulder Creek and
the North Fork South Platte based on its work plan (Figure 1), proposed objectives, and conceptual schedule.
The tasks described below will be the responsibility of the Consultant unless it is specified that Denver Water
or another entity will have the responsibility for said task(s). The tasks will be conducted in close coordination
with the Denver Water Team assigned to the task, including review and approval of draft and final deliverables.
The Consultant should consider the following SOW when evaluating the level of effort and support anticipated
by Denver Water for these activities. Work details may be adapted to changing conditions, major decisions,
and findings as the project work progresses. Consultants responding to this RFP should be willing to
collaboratively adjust work phases and tasks.
The project deliverables are described in further detail for each task.
Task 1: Project Management, Project Controls & Reporting, and Project Meetings
Task 2: Records Review and Data Requests
Task 3: Bank Stability Monitoring and Reporting
Task 4: Owner Directed Contingency
Task 1 – Project Management, Project Controls & Reporting, and Project Meetings
Task 1.1 – Project Management
Consultant shall appoint a Project Manager. The Consultant’s Project Manager shall oversee and administer
the project and manage all resources reporting to them. The Consultant’s Project Manager shall be the primary
point of contact with Denver Water’s Project Manager and should have awareness of all billable actions being
conducted by their team.
Task 1.2 – Project Controls & Reporting
Monthly invoices shall be prepared and submitted to Denver Water in an approved format. Invoices shall
include a Project Status Report and be submitted within 30 days of work being performed. Invoices shall be
broken down by task, Prime Consultant, and Subconsultants/Subcontractors, if any, and include the
following:
• Total contract amount.
• Detailed charges for the current invoice period (e.g. labor hours by individual and assigned labor rates;
itemized expenses).
• Total charges to date.
• Previous billings.
• Outstanding balance.
• Current amount remaining.
• Total amount due.
• Contract number.
The Consultant shall be responsible for the management of the Consultant and the Subconsultant (if any)
Project Team’s overall project controls, actively coordinating with Denver Water’s Project Manager to manage
the following:
Page 4 of 12
Gross Reservoir Expansion Project
Request for Proposal
• Project costs including forecasts.
• Project schedule.
• Document control.
Monthly project status reports shall be prepared and submitted to Denver Water as an attachment to the
monthly invoices. Project status reports should be in bullet format and concise. The reports shall include the
following:
• A summary of work completed since the previous report.
• The current project schedule and budget status.
• Project issues and potential change logs.
• Milestones and/or deliverables scheduled in the coming month.
This task also includes periodic project review by the Consultant’s management to ensure the project meets
Denver Water’s project objectives, is on schedule, and is within budget.
Task 1.3 – Project Meetings
Project meetings include the key Project Team Members and other stakeholders as needed for the current
topic. Unless specifically directed by Denver Water’s Project Manager, the Consultant will be responsible for
having the right team resources at the various meetings.
At a minimum, the proposal will account for participation in the following meetings:
(1) Kick-off meeting: Denver Water led.
− Frequency: N/A, onetime occurrence.
− Attendees: Denver Water PM, Consultant PM, key teammates as determined by respective PMs.
− Time: 1-hour.
− Agenda:
o Welcome/project background.
o Team introductions.
o Administration/logistics.
o High level schedule/deliverable review.
(2) Recurring Coordination Meetings: Denver Water led.
− Frequency: Two per year. One to discuss the yearly report and the second to discuss the current
year sampling plans.
− Attendees: Denver Water PM, Consultant PM, key teammates as determined by respective PMs
based on the topics/tasks being discussed.
− Time: 1-hr meetings.
− Agenda:
o Yearly Report – problems/challenges with the previous year sampling effort.
o Current Year Sampling – what changes have been implemented, any perceived problems?
o (As-needed) Budget/Invoice check-in: Discuss any overdue invoices, budget concerns,
changes with budget impacts, etc.
Note: Unless tasked or annotated otherwise, Denver Water will develop the meeting agendas and meeting
minutes for the kick-off meeting and the recurring meeting
Page 5 of 12
You are viewing the opportunity summary page, which includes a brief overview and a preview of the attached documents.
Disclaimer: The details regarding bids, requests for proposals (RFPs), and requests for qualifications (RFQs) on this site are provided for convenience and do not represent official public notice. To respond to or inquire about bids, RFPs, or RFQs, please contact the appropriate government department.
TRY FOR FREE
Not a GovernmentBidders Member Yet?
Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.
