Contract Time Estimate
2/26/2026
Page 1
Rd:
CSJ:
VARIOUS (SH 20)
0924-06-731
TASK
#
Description
1 PHASE 0: ADVANCED WARNING SIGNS AND SW3P
2 TCP SETUP
3 PREPARING ROW
4
5 PHASE 1: Segment 1 STA 10+00.00 to STA 62+80.00
6 RMV (2"-6") TRT/UNTRT BASE AND ASHPH PAV
7 D-GR HMA TY-C PG70-22
8 FL BS (CMP IN PLC)(TYD GR 4)(FNAL POS)
9 PRIME COAT (MULTI OPTION)
10 D-GR HMA TY-D PG70-22
11 CL C CONC (MISC)
12 CL A CONC (MISC) (HEADER CURB)
13 CONC CURB & GUTTER (TY II)
14 DRIVEWAYS (CONC)
15 CURB RAMPS (TY 7)
16
17 PHASE 2: Segment 2 STA 62+80.00 to STA 115+60.00
18 SW3P SETUP
19 FL BS (CMP IN PLC)(TYD GR 4)(FNAL POS)
20 PRIME COAT (MULTI OPTION)
21 D-GR HMA TY-D PG70-22
22 CL C CONC (MISC)
23 CL A CONC (MISC) (HEADER CURB)
24 CONC SIDEWALKS (4")
25 DRIVEWAYS (CONC)
26 14' PRE-FABRICATED BRIDGE
27 RRIPRAP (CONC) (4IN)
28 MOWSTRIP
29 MBGF
30
31 PHASE 3: Segment 3 STA 115+60.00 to STA 168+40.00
32 SW3P SETUP
33 FL BS (CMP IN PLC)(TYD GR 4)(FNAL POS)
34 PRIME COAT (MULTI OPTION)
35 D-GR HMA TY-D PG70-22
36 CL C CONC (MISC)
37 CL A CONC (MISC) (HEADER CURB)
38 DRIVEWAYS (CONC)
39 MOWSTRIP
40 MBGF
41
County:
EL PASO
Project: STP 2025(489)TAPS
#
3
= # Days / Cell
Quantity Unit
Daily
Rate
Pred % Start
Duration Task Compl Day
0
ete
1
Finish
Day
1
Au Sep Oct Nov Dec Jan Feb Mar Apr Ma Jun Jul Au Sep Oct
g (18) (18) (18) (18) (18) (18) (18) (18) y (18) (18) g (18) (18)
1 DAY 1
1
1 10
1
1
218 STA 6
37
2 10
2
38
0
2
2
0
2
2
250 SY 2450
1
3 20 10
10
23 TON 1000
1
6 100 11
11
990 CY 500
2
7 100 12
13
921 GAL 1000
1
8 100 14
14
656 TON 1000
1
9 100 15
15
21 SY 132
5,013 CY 165
1
10 100 16
16
31
11 100 17
47
120 LF 288
1
12 90 45
45
89 SY 132
1
13 100 46
46
1 EA
3
1
14 100 47
47
0
47
47
0
47
47
1 DAY 1
1,185 CY 500
1
15 0
47
47
3
18 100 48
50
952 GAL 1000
1
19 100 51
51
784 TON 1000
1
20 100 52
52
28 SY 132
1
21 100 53
53
5,205 CY 165
12 SY 132
32
22 100 54
85
1
23 90 83
83
136 SY 132
2
24 100 84
85
60 LF 1.95
31
25 100 86 116
99 CY 175
1
26 100 117 117
97 SY 523
1
27 100 118 118
250 LF 1000
1
28 100 119 119
0
119 119
0
119 119
1 DAY 1
1
29 0 119 119
1,042 CY 500
3
32 100 120 122
1,250 GAL 1000
2
33 100 123 124
688 TON 1000
1
34 100 125 125
64 SY 132
1
35 100 126 126
5,114 CY 165
31
36 100 127 157
305 SY 132
3
37 90 155 157
97 SY 523
1
38 100 158 158
250 LF 1000
1
39 100 159 159
0
159 159
https://aecom.sharepoint.com/sites/CRRMA2022/Shared Documents/Ph3 Alamo Alto SUP (Fabens-Tornillo)/RTL_Deliverable (Live Forms)/092406731_100_2026.02.25/Supporting Documents/07 Contract Time Determination.xlsm
TASK
#
Description
42 PHASE 4: Segment 4 STA 168+40.00 to STA 228+74.19.00
43 SW3P SETUP
44 FL BS (CMP IN PLC)(TYD GR 4)(FNAL POS)
45 PRIME COAT (MULTI OPTION)
46 D-GR HMA TY-D PG70-22
47 CL C CONC (MISC)
48 CL A CONC (MISC) (HEADER CURB)
49 DRIVEWAYS (CONC)
50 MOWSTRIP
51 MBGF
52
53 PHASE 5: Signing and Pavement Markings
54 DRILL SHAFT (24IN)
55 DRILL SHAFT ROADWAY ILLUM POLE (30IN)
56 REFL PAV MRK TY I (W) 24" (SLD) (100MIL)
57 REFL PAV MRK TY I (W)(SYMBOL)(100MIL)
58 REFL PAV MRK TY I (W)(BIKE ARW)(100MIL)
59 REFL PAV MRK TY I(W)(BIKE SYML)(100MIL)
60 RE PM TY II (W) 4" (BRK)
61 RE PM TY II (W) 24" (SLD)
62 RE PM TY II (W) (SYMBOL)
63 RE PM TY II (W) (BIKE ARROW)
64 RE PM TY II (W) (BIKE SYMBOL)
65 RE PM TY II (Y) 4" (BRK)
66 REFL PAV MRK TY I (W)4"(BRK)(100MIL)
67 REFL PAV MRK TY I (Y)4"(BRK)(100MIL)
68 36" BIKE BOLLARD (YELLOW)
69 REPLACE ALUM SIGN PANELS
70 PERMANENT SIGNS
71 SOIL STABILIZER
72 PROJECT CLOSEOUT
SCHEDULE IS BASED ON:
May 6, 2026 Letting
Approximately 2 Months Notice to Proceed
30 Calendar Days to Begin Work
Standard Work Week (Item 8.3.1.4)
18 Days per Month
15 Months for Barricades and Traffic Handling (Item 502)
258 Working Days
Proposed Construction Start Date: August 4, 2026
(90 Days after letting)
Estimated Construction End Date = November 4, 2027
W = Computed Work Time (Contractor Operations,
Production Rates, Sequencing) = 258wd
A = Available Work Day per Month = 18 days
B = Barricade & Traffic Handling Time (Pay Item 502) =
W/A = 258/18 = 14.33 ~ 15 months
Quantity Unit
1
1,231
1,477
813
21
6,043
70
175
450
DAY
CY
GAL
TON
SY
CY
SY
SY
LF
1,044
30
62
4
4
4
78
62
4
4
4
129
78
5,460
24
4
31
23,874
1
LF
LF
LF
EA
EA
EA
LF
LF
EA
EA
EA
LF
LF
LF
EA
EA
EA
SY
DAY
Daily
Rate
1
500
1000
1000
132
165
132
523
1000
104
10
12500
1000
1000
1000
12500
12500
1000
1000
1000
12500
12500
12500
20
15
10
1,000
100
Pred %
Duration Task Compl
0
ete
1
40 100
3
43 100
2
44 100
1
45 100
1
46 100
37
47 100
1
48 90
1
49 100
1
50 100
0
0
11
51 0
3
54 100
1
55 75
1
56 100
1
57 100
1
58 100
1
59 100
1
60 100
1
61 100
1
62 100
1
63 100
1
64 100
1
65 100
1
66 100
2
67 100
1
68 50
4
69 0
24
70 60
1
71 100
Start
Day
159
160
161
164
166
167
168
202
203
204
204
204
204
215
218
219
220
221
222
223
224
225
226
227
228
229
230
231
231
234
258
Finish
Day
159
160
163
165
166
167
204
202
203
204
204
204
214
217
218
219
220
221
222
223
224
225
226
227
228
229
231
231
234
257
258
2/26/2026
Page 2
Au Sep Oct Nov Dec Jan Feb Mar Apr Ma Jun Jul Au Sep Oct
g (18) (18) (18) (18) (18) (18) (18) (18) y (18) (18) g (18) (18)
02/26/2026
https://aecom.sharepoint.com/sites/CRRMA2022/Shared Documents/Ph3 Alamo Alto SUP (Fabens-Tornillo)/RTL_Deliverable (Live Forms)/092406731_100_2026.02.25/Supporting Documents/07 Contract Time Determination.xlsm
You are viewing the opportunity summary page, which includes a brief overview and a preview of the attached documents.
Disclaimer: The details regarding bids, requests for proposals (RFPs), and requests for qualifications (RFQs) on this site are provided for convenience and do not represent official public notice. To respond to or inquire about bids, RFPs, or RFQs, please contact the appropriate government department.

TRY FOR FREE

Not a GovernmentBidders Member Yet?

Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.

Start Free Trial Today >