CES Expansion UPS Upgrade
| Bidders ID: | NBD00159845888189195 |
|---|---|
| Due Date: | Aug 25, 2026 |
| Posted Date: | Aug 12, 2026 |
| Level of Government: | Federal |
| State: | Illinois |
| Agency: | DEPT OF DEFENSE |
| Category: |
|
| Solicitation Number: | W91SMC26QA016 |
| Source: | Members Only |
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
- Contract Opportunity Type: Solicitation (Updated)
- Updated Published Date: Aug 12, 2026 01:17 pm CDT
- Original Published Date: Jul 27, 2026 01:40 pm CDT
- Updated Date Offers Due: Aug 25, 2026 11:00 am CDT
- Original Date Offers Due: Aug 25, 2026 11:00 am CDT
- Inactive Policy: 15 days after date offers due
- Updated Inactive Date: Sep 09, 2026
- Original Inactive Date: Sep 09, 2026
-
Initiative:
- None
- Original Set Aside: Total Small Business Set-Aside (FAR 19.5)
- Product Service Code: Y1AZ - CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS
-
NAICS Code:
- 236220 - Commercial and Institutional Building Construction
-
Place of Performance:
Springfield , ILUSA
*Edit 8/12/26 - added Slides and Minutes from Pre-Quote Conference and Site Visit.*
The 183d Wing (183WG) at the Abraham Lincoln Capital Airport, Air National Guard Base, Springfield, IL, has a requirement for a firm-fixed-price construction contract to upgrade the Uninterrupted Power Supply (UPS) system in Building 8.
SITE VISIT - 11 AUG 2026 @ 1300.
The contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, and non-personal services necessary to remove the existing 10 kW UPS system and install a new scalable 20 kW UPS system.
Key scope items include:
- Demolition and removal of one (1) existing 10 kW Liebert EXM UPS in SWITCH Room 118, including associated equipment and maintenance bypass panelboard.
- Site and electrical preparation for the new system.
- Installation of one (1) new scalable 20 kW UPS System (configured for 20 kVA/kW, scalable up to 30 kVA/kW for future expansion).
- Sealing of all wall/floor/ceiling penetrations to meet existing fire and assembly ratings.
- Full system adjustments, load balancing, and operational testing by factory-trained field service personnel.
Period of Performance: 120 days or less after issuance of Notice to Proceed (NTP).
See Solicitation for additional information.
- 1301 N MACARTHUR BLVD CCDF
- SPRINGFIELD , IL 62702-2399
- USA
- Lawrence Romang
- lawrence.j.romang.civ@army.mil
- Phone Number 2177613462
- Aug 12, 2026 01:17 pm CDTSolicitation (Updated)
- Jul 27, 2026 01:40 pm CDT Solicitation (Original)
- Jul 08, 2026 02:37 pm CDT Presolicitation (Updated)
Related Document
| Jul 27, 2026 | [Solicitation (Original)] CES Expansion UPS Upgrade |
TRY FOR FREE
Not a GovernmentBidders Member Yet?
Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.